Renewable Portfolio Standards(RPS)

Purpose

This system mandates power producers that have power generating facilities with installed capacity over 500MW to produce a minimum proportion of their power using new and renewable energy sources.

Legal basis
  • The Act on the Promotion of the Deployment, Use and Diffusion of New and Renewable Energy (Law no. 12296)
  • The Guidelines on the Management and Operation of Obligatory Renewable Energy Supply Program (MOITE Notification no.2014-164)
  • The Regulation on the Issuance of Renewable Energy Certificate and the Operation of the Certificate Market (NREC Notification 2014-22)
Details of the program
Power producers subject to the system

Korea Hydro & Nuclear Power, Korea South East Power, Korea Midland Power, Korea Western Power, Korea South Power, Korea East-West Power, Korea District Heating Corporation, K water, SK E&&S, GS EPS, GS Power, Posco Energy, MPC Yulchon Power, Pyungtaek Energy Service

Annual RPS Target

Obligatory renewable service supply ratio (Additional table no.3 of Enforcement Ordinance of the Act on the Promotion of the Deployment, Use and Diffusion of New and Renewable Energy )

Annual RPS Target
Year ‘12 ‘13 ‘14 ‘15 ‘16 ‘17 ‘18 ‘19 ‘20 ‘21 ‘22~
Ratio(%) 2.0 2.5 3.0 3.2 4.0 5.0 6.0 7.0 8.0 9.0 10

※ Total power generation (new and renewable energy generation excluded) X obligatory supply ratio

Solar PV power obligation supply

Obligatory solar PV supply (Additional table no.4 of Enforcement Ordinance of the Act on the Promotion of the Deployment, Use and Diffusion of New and Renewable Energy )

Solar PV power obligation supply
Year ‘12 ‘13 ‘24 ‘15~
Obligatory supply (GWh) 276 723 1,353 1,971

※ Solar PV supply obligation is to be applied until December 31, 2015 (The article 18, clause 3 of the New and Renewable Energy Act)

※ A plan to combine Solar PV and non-solar PV energy obligations from 2016 is under review

Penalties for non-compliance

Penalties of maxim of 150% of trading prices of renewable energy supply certificate are imposed for non-compliance. The amount of penalties varies depending on causes and frequency of the non-compliance.

Differing the supply of obligatory new and renewable energy supply

The obligatory supply can be deferred for maximum 3 years. The deferred amount is maximum 20% of the obligatory supply.

Renewable Energy Certificate (REC)
  • REC certifies that power generators produced and supplied power using new and renewable energy facilities
  • Power generators can meet their obligatory new and renewable energy supply target by purchasing REC
  • REC is issued based on the weighted new and renewable energy supply (MWh)
REC weighting scheme
REC weighting scheme
category REC weighting Energy source and criteria
Facility type Criteria
Solar PV 1.2 Facility installed
on general site
Less than 100kW
1.0 More than 100kW
0.7 More than 3,000kW
1.5 Facility installed
on existing buildings
Less than 3,000kW
1.0 More than 3,000kW
1.5 Facilities floating on the water
Others 0.25 IGCCC, Byproduct gas
0.5 Waste, landfill gas
1.0 Hydro, onshore wind, bioenergy, RDF, waste gasification,
tidal power (with embankment)
1.5 Wood biomass, offshore wind (grid connection less than 5km)
2.0 Fuel cell, tidal power
2.0 Offshore wind (grid connection
longer than 5km), geothermal,
tidal power (no embankment)
Fixed
1.0~2.5 Variable
5.5 ESS (connected to wind power) ‘15
5.0 ‘16
4.5 ‘17