contents

home ENERGY EFFICIENCY Industry Inspection for Imported Machinery and Equipment subject to Inspection

Inspection for Imported Machinery and Equipment subject to Inspection

link to Application

Legal Ground

- Energy Use Rationalization Act, Article 39-2 (Inspection of Imported Machinery and Equipment subject to Inspection)

- Date of enforcement : Dec. 3, 2017

- Applicant for Inspection & Fee Payer : Manufacturer

Machinery and Equipment subject to inspection (Enforcement regulations of Energy Use Rationalization Act, Article 31-6)
Boiler
  • Power boiler : water tube, fire tube, etc.
  • Heating boiler
Pressure vessel
  • class 1 pressure vessel
  • class 2 pressure vessel
  • ※ See applicable Provisions for details
Type of inspection and application (Enforcement regulations of Energy Use Rationalization Act, Article 31-7)
Welding Inspection, W.I.
  • Inspection in case of fabrication of body, end plate and similar parts by welding, plus design Inspeciton
  • Application Documents
    • - Welding diagram, 1copy

    • - Design drawing 2copies

    • - Strength Calculation sheet, 1copy

  • Structural Inspection, S.I.
    • Inspection when fabricating steel sheet, tube or casting current by welding, expansion, assembly, casting, etc. , plus design Inspeciton.
    • Application Documents : Certificate of Welding Inspection 1copy. 1 set document of Welding Inspection will be required to summit, in case of exemption items of Welding Inspection.
Inspection Standard (Enforcement regulations of Energy Use Rationalization Act, Article 31-9)
  • KS Code
  • Notification of the Ministry